| Travis County Feasibility Study and Implementation Plan (Mobility35 Plan) | SH 45N to SH 45SE | 2 | TxDOT and State of Texas (Rider 42) | N/A | Study complete, refinements ongoing |
| Future Transportation Corridor Planning & Environmental Linkages Study | SH 45N to SH 45SE | 2 | TxDOT, city of Austin and State of Texas (Rider 42) | N/A | Stand-alone projects will be recommended for inclusion in the CAMPO Long Range Plan and advanced into environmental/design studies |
| Northbound Collector-Distributor (C-D) Road | Howard Lane to Parmer Lane | 5 | TxDOT and private | $3M | Construction completion anticipated 2015 |
| Direct Connectors | I-35 at US 183 | 3 | TxDOT funding Phase 3 Construction not currently funded | $105M | Public Open Houses anticipated early 2015 |
| Mainlane, Frontage Road & Intersection Operational Improvements | US 183 to US 290 | 3 | TxDOT funding Phase 3 Construction not currently funded | $65M | Public Open Houses anticipated early 2015 |
Southbound Frontage Road & Intersection Operational Improvements
| I-35 at 51st St. | 3 | TxDOT and city of Austin funding Phase 3 Construction not currently funded
| $13M
| Public Open House scheduled for February 12, 2015
Virtual Open House available now
|
| Northbound Frontage Road & Intersection Operational Improvements | I-35 at 53rd St. | 5 | 2010 Transportation Bond - primary source for construction | $3M | Construction completion anticipated by the end of 2015 |
| Initial Concept Development | I-35 through the Decks | 2 | TxDOT funding Phase 2 Construction not currently funded | N/A | Ongoing neighborhood and stakeholder outreach |
| Initial Concept Development | I-35 through Downtown | 2 | TxDOT funding Phase 2 Construction not currently funded | N/A | Ongoing neighborhood and stakeholder outreach |
| Mainlane, Frontage Road & Intersection Operational Improvements | I-35 at Riverside Drive | 3 | TxDOT funding Phase 3 Construction not currently funded | $84M | Public Open Houses anticipated 2015 |
| Mainlane, Frontage Road & Intersection Operational Improvements | I-35 at Oltorf Street | 3 & 4 | TxDOT funding Phase 3, 4 Construction not currently funded | $39M | Finish schematic and environmental efforts anticipated by end of 2014 |
| Mainlane, Frontage Road & Intersection Operational Improvements | I-35 at William Cannon Drive and Stassney Lane | 3 & 4 | TxDOT funding Phase 3, 4 Construction not currently funded | $61M | Finish schematic and environmental efforts anticipated by end of 2014 |