Mobility35 Hays County Projects

 



Project


Limits

Current
Phase*

Funding Source

Estimated
Construction Cost


Upcoming Milestone
Hays County Feasibility StudySH 45SE to Posey Road2CAMPO STPMM funds for Phase 2N/A​Third series of Open Houses, anticipated early 2015
Ramp Reversals and Intersection Operational Improvements​FM 2001 to FM 1505Hays County Road Bond
Pass-Through Financing Agreement with TxDOT
$16MConstruction completion anticipated spring 2015
Bridge Replacement & Corridor ImprovementsI-35 at Yarrington Road5Hays County Road Bond
Pass-Through Financing Agreement with TxDOT
$16MConstruction completion, andticipated spring 2015
Ramp Reversals​FM 150 to Blanco River3TxDOT funding Phase 3
Construction not currently funded
$12MFinalize schematic and environmental documentation
Intersection Operational ImprovementsI-35 at SH 80 and Loop 825Traditional development funded by TxDOT$6MConstruction complete; project open to traffic
Mainlane, Frontage Road & Intersection Operational Improvements​
I-35 at Posey Road3 & 4Hays County - TxDOT Partnership Program$18MFinalize environmental documentation, anticipated early 2015
*Learn more about Project Phasing​

Download our Mobility35 Fact Sheet​ for an overview of each project within the corridor. 