SH 45 North to SH 45 Southeast

Overview:

A Planning and Environmental Linkages Study (PEL) is an environmental process used to determine the purpose and need, lane type alternative/mode choice, and segments of independent utility for the Future Transportation Corridor (FTC) between SH 45N and SH 45SE.

Need & Purpose
  • Develop a purpose and need for the FTC
  • Determine the lane type alternative/mode choice
  • Determine segments of independent utility (segments that have benefit and can be constructed as stand-alone projects)
End Result
  • FTC lane mode recommendation determination
  • Recommend projects for inclusion in the Capital Area Metropolitan Planning Organization 2040 Regional Transportation Plan
Funding
  • Funding for the study is provided by TxDOT, city of Austin and the state of Texas (Rider 42 funds)
  • Funding for further concept development and construction may be provided by TxDOT and/or one of the Agency's transportation partners
Schedule
  • Study start: June 2014
  • Public Open Houses: June 2014, September 2014
  • Study completion: anticipated end of 2014

Project Vicinity Map

Contact

Public Information Officer

TxDOT Austin District
P.O. Drawer 15426
Austin, TX 78761-5426

(512) 832-7000

Email